[Charles House] “I’m reading about Cinema Tools and Compressor potentially being able to solve this issue. I’ve tried JES Deinterlacer, and it seems to help, but also add some blur. I am also not aware of how do alter the settings as per my footage, if that’s something I’d need to do to get the best results. Are any of these options for me?”
The problem is that your footage, as it is currently edited together, is a hybrid of both interlaced and progressive footage – it is neither purely interlaced nor progressive. If you attempt to deinterlace it, you will degrade the progressive frames.
Cinema Tools can remove pulldown on individual 24p clips shot with with 3:2 pulldown, but it requires some manual guidance. You will need to specify an A frame first before the shot can be conformed to 24p – read the manual for a complete explanation. Conforming must be done on a per-clip basis, not on a completed edit.
You can’t remove the pulldown on the entire edit all at once because the pulldown cadence (a repeating pattern of three progressive frames followed by two split, interlaced frames) will not necessarily remain constant through an edit. For example, the cadence of progressive whole frames (W) and interlaced split frames (S) may be W/W/W/S/S on one shot and W/S/S/W/W on the next, followed by W/W/S/S/W on the next. If you attempt to remove pulldown on a single file containing cadence changes, you will butcher the footage and end up with a bizarre mix of 24p segments followed by interlaced segments with no consistent pattern or pulldown present. There is no way that Cinema Tools can automatically determine the cadence as it changes. This is why it’s critical to remove the pulldown prior to editing.
Compressor also has the ability to remove pulldown, but I don’t believe it can automatically detect and remove pulldown on a file that contains a changing cadence. I’m not positive about that, however.
I am highly skeptical that there is an automatic toggle function that can legitimately fix this in Premiere.
In the future, the correct workflow for working with a DVX100 would be to shoot 24pA and let Final Cut Pro automatically remove the Advanced pulldown upon capturing the footage, then edit in a native 24p sequence.
If you have to go back and try to fix what you have already shot, the necessary workflow would be to first go back and individually conform all of your captured clips to 24p using Cinema Tools or Compressor. You would first need to ensure that each captured clip had an unbroken cadence. If they did not, you’d have to either recapture the footage by logging and capturing individual clips or manually cut up the captured clips into separate clips with unbroken cadence. Once you conformed all of the original clips to 24p, you would then have to manually recreate your original edit in a 24p sequence.
It’s a staggering amount of work, which is why I said that it’s a tough lesson to learn. It’s also a great reason to shoot 24pA and not regular 24p, because FCP can automatically remove Advanced Pulldown on capture, whereas normal 3:2 pulldown must be removed on a per-clip basis using Cinema Tools or Compressor.
At this point, you should probably just author the DVD as-is and live with the fact that it’s 24p over 29.97i with 3:2 pulldown. It will look fine when played back on DVD players. You see movies on TV all the time that are 24p with 3:2 pulldown played back in a 29.97 interlaced signal and you don’t even notice it.