  • Peter Normandia

    September 16, 2013 at 2:58 pm in reply to: Premiere cc – strange lag on playhead when scrubbing

    Ok, just for anyone else experiencing something similar, I thought I would update.

    Yes, it has to be the footage.

    However, I have shot footage before and after with all the same pieces (gh3, San Disk extreme sd card). All were shot at 60p in AVCHD.

    The only difference that I can gather is before shooting my footage, on the same card, I shot a timelapse of the setup for the party. I’m assuming somehow that caused the footage’s timecode to be off, which in turn caused this issue.

    Again, this is just speculation, but I can’t imagine what else it could possibly be.

  • Peter Normandia

    September 16, 2013 at 2:17 pm in reply to: Premiere cc – strange lag on playhead when scrubbing

    Thanks Dennis. I’m running RAID 5 on an enclosure attached via Esata to my mid 2010 mac pro.

    I ran disk utility on the enclosure and everything came back great. So I opened up another premiere project (with the same type of footage AVCHD), that was running off a different drive and the problem was fixed.

    Believing it was the RAID, I move the project to that drive and made my post. However, when I opened the project on the other drive, I was faced with the same issue.

    I’m assuming it has to be the footage in the project, but I can’t imagine what makes this project different then the 12-15 just like it I recently finished.

  • Peter Normandia

    September 16, 2013 at 12:27 pm in reply to: Premiere cc – strange lag on playhead when scrubbing

    Upon further inspection, I am pretty sure its my RAID. But what am I to do. It is less then 50% full after I cleared over a 1/2 of TB. Is there a way to update/optimize it?

  • Peter Normandia

    September 13, 2013 at 10:42 pm in reply to: Premiere cc – strange lag on playhead when scrubbing

    I have the exact same issue, with a 50% full RAID and AVC HD Footage. Very strange. Did your digital time clock add some extra digits as well?

    First, my ‘clock’ (for lack of a better term this is the digital numbers representing the playhead position in the top right of the timeline), was appearing like 00+0.

    Then after I adjusted some settings right on the actual sequence (specifically clicked on show Audio units), the ‘clock’ appeared back in the top right, but this time with 3 extra digits.

    Clock reads 00:36:40:38115 – when i scrub it goes up only one digit at a time (38116, 38117, etc.)

    Any help appreciated