    Posted by Frank Raposo on September 3, 2013 at 7:08 pm

    I created an 8 minute comp (7552×552) at 29.97. The client wants is at 59.94, 24 bit Targa sequence. After I export my final comp, I re-import the Targa sequence to check for errors and my 8 minute video is 16 minutes. I’ve change the frame rate to 59.94 in the render settings, with no luck. I changed the actual comp settings to 59.94 and still get the same results. I’ve tried dropping my final comp into another 59.94 comp and render it out that way but I still get a 16 minute video when I re-import my Targa sequence.

    I’ve also tried changing the field rendering. I’ve exported with it off and with Upper field and I still get a 16 minute Targa sequence. I’ve never exported a Targa sequence out of AE before so I really don’t know what I’m doing wrong. Any help would be greatly appreciated.

    quinnmcguee

    Walter Soyka replied 12 years, 8 months ago 2 Members · 1 Reply
  • 1 Reply
  • Walter Soyka

    September 3, 2013 at 8:26 pm

    Image sequences do not store any information about framerate. Because of this, After Effects applies a default framerate, specified under “Sequence Footage” in After Effects > Preferences > Import.

    You can override that guess by right-clicking your imported sequence and using Interpret footage [link] to change its frame rate.

    Walter Soyka
    Principal & Designer at Keen Live
    Motion Graphics, Widescreen Events, Presentation Design, and Consulting
    RenderBreak Blog – What I’m thinking when my workstation’s thinking
    Creative Cow Forum Host: Live & Stage Events

We use anonymous cookies to give you the best experience we can.
Our Privacy policy | GDPR Policy